ESA Ignores Science And Facts,
Environmental Consultants Say
By Colleen Schreiber
AUSTIN "Biomythology is running rampant in
Austin, Texas."
That was the message environmental consultant Steve
Paulson delivered to participants in the recent
Endangered Species Act Conference sponsored by CLE
International. His topic focused on the use or misuse of
science as it relates to the federal Endangered Species
Act.
"Ive been very critical of the use of
science by the Fish and Wildlife Service," he told
listeners.
The Act says endangered species should be held to the
highest protection. That alone, Paulson told listeners,
places a heavy burden on science.
"Lots of times, attorneys tend to want to make
this a legal issue. Biology should be decided based on
science. Instead, science and the scientific method have
been severely abused," he said.
Section 4 of the Endangered Species Act defines
reasons for the listing of a species as endangered. Those
reasons include: reduction in a population, shrinking
range, overutilization, predation, etc. Listing can be
based on any one of these issues, Paulson noted.
"Where do you draw the line, though? For example,
there is a reduction in all neotropical migratory birds,
so which ones do you decide to list and how do you go
about making that decision?" he asked.
When the five karst invertebrates (insects living in a
particular series of caves and fissures) in Travis County
were listed, it was originally said that they could only
be found in seven caves in Travis County. Later
scientists found that they were actually found in about
25 percent of the 500-some caves in Travis County, and
now theyre known to be found in over 100 caves.
"Does that still mean that theyre
endangered?" Paulson queried. "Theres
also a signed affidavit that says there were only seven
or nine Barton Springs salamanders left when it was
listed. Now the city is proposing to take up to 200
salamanders a year through their pool cleaning
activities."
In addition, when the golden-cheeked warbler was
listed, scientists said the birds needed a patch size of
at least 125 acres with 75 percent cover to be viable
habitat, and that anything less than that was not
sufficient. Yet in the listing package, the patch size
was reduced to 50 acres and 35 percent canopy cover.
He cited another example which skews the listing
criteria. A recovery plan for an endangered warbler in
Michigan says that once 1000 nesting pair are recovered,
the species can be delisted. Yet in Texas, the recovery
plan for the Golden-cheeked warbler requires something
like 15,000 nesting pairs before it can be taken off the
list.
"Whats the difference?" Paulson asked
listeners. "Ive read both of those recovery
plans and theyre both very well written, but they
both come to different conclusions about the viability of
the species."
The Act allows for "incidental" take using a
Section 10(a) permit. The permit includes a list of
activities required of the permittee. One is writing a
habitat conservation plan and another is
"mitigation" for species to be
"taken."
"We have people buying habitat for the warbler,
but we dont know if it works. We have ashe juniper
taking over the hill country, and in 50 years western
Travis County will be a monoculture of juniper trees if
we dont spend any money in operation and
maintenance to eliminate juniper trees. Will that be good
for the birds?"
Paulson told listeners that one of the ESA
reauthorization bills, the Miller bill, puts more and
more burden on landowners to pay for the perpetuation or
recovery of a species.
"Its not the responsibility of the last
person down the line to pay for it," Paulson said.
"Its our responsibility to pay for it. So I
would still recommend going with species by species
funding until we get the appropriate funding and get the
science in order."
He noted that the other part about the biology that
needs fixing, in his opinion, is that there is totally
inequitable access to the biological information process
in terms of data information given to the respective
parties.
"Landowners cant get any information about
the species from the F&WS, and yet time and time
again weve heard that the environmentalists already
have the information."
As an example, he told listeners about attempts to get
DNA information on the Barton Springs salamander.
"For many years it was considered the Texas
salamander, and then in 1979 a scientist declared it to
be the Barton Springs salamander. The F&WS
immediately put it on the "to-list" list
without any separate analysis to determine if it was in
fact a different species," he noted. "Then,
just before it was listed, a couple of scientists
provided information about the DNA which proved that it
was a separate species. We asked for that DNA analysis,
but they wouldnt release that information. There is
inequity about releasing information," Paulson
stressed.
Lee Sherrod, consulting biologist with Horizon
Environmental Services, also in Austin, backed up some of
his fellow consultants comments about how science
is used in the endangered species saga.
Sherrods presentation focused on how to get a
project underway when confronted by the Endangered
Species Act. He focused specifically on the Section 10(a)
permitting process as it applies to private individuals
and any non-federal entity.
"There have been several endangered species that
have been placed on the list that have caused what I
would call havoc in the Austin area,"
Sherrod told listeners.
The environmental consultant first outlined the nuts
and bolts of the permitting process, including a lengthy
list of forms, plans, agreements and guarantees
all on the part of the permittee. The government makes no
guarantees, or none that will hold up.
Permitting, Sherrod said, "can take years to
accomplish and may require lengthy and costly
environmental studies to document the level of take of
listed species. There are no time lines for processing
these permits. In essence, they get processed when
F&WS gets around to it."
He also provided a condensed case history of the first
10(a) permit processed in Texas, or in the entire
F&WS Albuquerque region, for that matter. At the
time, it was one of fewer than two dozen permits that had
been issued nationwide.
The story took place in Austin and actually begin in
the early 1980s. Simon Property Group, a nationwide
development company, purchased a 116-acre site on the
northwest side of Austin near Cedar Park in anticipation
of development expanding out that way at a major
intersection highways 620 and 183. Their goal was
to build one of the largest retail shopping malls in the
Southwestern U.S.
The Austin area was then at the apex of a growth boom
and the vicinity of the mall site was rapidly urbanizing,
in effect blending the City of Austin with the cities of
Cedar Park and Round Rock to the north into a metroplex,
Sherrod said.
SPG proceeded with site design and local development
approval through the City of Austin, which in itself was
an arduous and lengthy process requiring several years
for a major project such as the mall. The site was
located within a geologic formation associated with
recharge of an environmentally sensitive aquifer. To
develop in this geologic formation, local development
codes required detailed geologic assessment to determine
the presence of significant aquifer recharge features
(caves, sinks, fissures, etc., termed "karst
features"). Detailed geologic studies of the site
were conducted, and though numerous karst features were
documented on the site including several caves and large
sinks, it was concluded that the on-site karst features
were not significant from an aquifer recharge standpoint.
This assessment, Sherrod said, in part cleared the way
for local development approvals. By late 1989, site
design was complete and local approvals were imminent.
Construction of the mall was anticipated to begin in
early 1990.
Then things changed. At the time the developers bought
the site, the cave invertebrates, the speaker noted, were
not listed as endangered species. The usual
development/environmental battle, however, was going
strong in the Austin area during this time.
In the fracas, two species of birds and five species
of cave-dwelling invertebrate organisms were listed by
F&WS as endangered species. When listed in 1988, the
cave invertebrates were thought to be restricted to just
a few caves located in a relatively small geographic area
on the west side of Austin and a few isolated outliers in
the country to the north. These species were not then
known to occur in the immediate vicinity of the mall
site.
By 1990 the company had pretty well completed all its
local approval, they had all their funding set up, and
they were getting ready to start construction in just a
few months. In the meantime, a couple of spelunkers had
been looking in some caves on the mall site and found
what they thought was one of the listed species known to
live several miles to the south. This particular cave was
not on the site itself but immediately adjacent to it.
SPG notified F&WS and they then contracted with a
researcher to confirm that this was one of the listed
species. The researcher confirmed that the invertebrate
was in fact the tooth cave ground beetle. While in the
cave, he also found another listed karst species.
F&WS then notified the mall developer that there
were endangered species on the mall site and that the
development of the mall could in essence effect a
"take." Additionally, some of these species
could possibly be found in other caves on the mall site.
At this point, nearly six months had transpired and the
mall project was now indefinitely delayed.
SPG conducted extensive discussions with F&WS to
evaluate alternatives for moving forward with the
proposed mall project. The only options left to pursue
were either to cancel the mall project or proceed into a
then rarely utilized provision of the Endangered Species
Act a 10(a) permit for incidental take. They
decided on the latter option despite great uncertainties
as to timeframes or costs, Sherrod said.
To proceed with the permit, the developers had to
determine how much of the mall site potentially contained
subsurface habitat for the species. Thus, after still
more months of extensive studies, it was determined that
only the eastern half of the mall site, about 62 acres,
would be potential habitat for the listed species.
The company plowed on through the permit process and
two years later they finally came out on the other side.
F&WS came up with mitigation requirements, which
ended up costing the developers four acres of
"mitigation" habitat for each acre utilized,
Sherrod told the group.
At that point SPG initiated the process of locating
suitable endangered cave invertebrate habitat that could
be purchased for preserves. The geologic formation
containing caves covered many thousands of acres, and it
was initially thought that finding the required amount of
acreage (234 acres) with documented occurrences of both
the Tooth Cave ground beetle and Bone Cave harvestman
would not be a formidable task. However, as it turned
out, the Lakeline area and a narrow zone stretching a few
miles to the south were the only areas in which the two
species ranges overlapped. Due to exploding
development, this land was some of the most expensive
real estate in the Austin area.
It was determined that separate preserves would have
to be obtained for each species. The search continued.
The landowners of all previously documented caves
containing one or the other of these two species were
contacted to determine availability of the tracts for
sale.
About 45 landowners were contacted, but none resulted
in a potential purchase. Either they were not willing to
sell because they wanted to maintain their own potential
mitigation; their asking price was economically
infeasible for the Lakeline project; the parcels were too
big and the owner would not subdivide; or the parcel was
too small to be considered a viable cave preserve tract.
The months were still passing and as yet resolution to
the permit was not in sight.
After another six or so months, the company finally
found suitable mitigation acreage for both species on
three separate parcels within the two-county area. The
permit process took another step forward.
The permit was finally issued in January 1992, fully
two years after the discovery of the species in Lakeline
Cave. The mitigation for the 62 acres, Sherrod noted,
came with a big price tag, both in dollars and time
expired. "Everyone thought this was a monumental
achievement. The revelry for the mall people, however,
didnt last long because it had been two years and
they essentially had lost their funding," he said.
"The economy, both nationally and locally had
changed, and their financing package that had originally
been secured to build the mall in 1990 had long expired.
They had also lost some of their tenants. Thus, SPG
essentially had to go back to square one."
The developer went back to the drawing board,
essentially redraw the project, and another three years
passed before the mall project was back to the point of
being ready to break ground. In early 1995, construction
finally began and the mall opened for business in October
of that year. In essence, the endangered species issues
resulted in nearly six years of delay and several million
dollars in direct and indirect costs for the mall
project.
|